Many plants restart motors after weeks or months of shutdown - and a surprising number burn out within minutes. The culprits are rarely mechanical: moisture in the windings, dropped insulation resistance, dried-out grease, and debris in the terminal box. This guide gives a practical pre-start checklist that prevents most restart failures.

SHANGDIAN motor pre-start inspection after long shutdown

1. Why Long-Dormant Motors Fail on Restart

During storage, windings absorb moisture from the air and insulation resistance drops; bearing grease slowly dries and separates; dust, insects or rodents can enter the terminal box; and corrosion can make the rotor stiff. Starting at full voltage without clearing these issues can trip the breaker or - worse - puncture the winding insulation and burn the motor out.

2. Pre-Start Checklist: 5 Steps Before You Power Up

CheckHowAcceptanceIf not OK
1. Housing & terminal boxOpen terminal box; check terminals, cables for looseness, corrosion, foreign objectsTerminals tight, no oxidation, cleanClean, retighten, replace terminals if needed
2. Insulation resistanceMeasure winding-to-ground with a 500 V megger (phase-to-phase if required)≥1 MΩ (generally ≥0.5 MΩ acceptable)Dry the motor first, then re-test
3. Bearing lubricationTurn rotor by hand; listen for noise; inspect greaseFree rotation, no abnormal noiseRegrease or clean and repack - see our bearing grease guide
4. Ventilation pathCheck fan cover, cooling fins, fan blades for blockage or damageAir path clear, blades intactRemove debris, replace damaged blades
5. No-load trial runStart uncoupled (or disengaged); run 30-60 minNo noise, no overheating, balanced phase currentsStop and investigate; contact the manufacturer

3. Insulation Resistance Too Low? Dry Before Starting

Never energize a motor whose insulation resistance is below 0.5 MΩ after storage. Common drying methods:

  • Natural drying: Place in a ventilated dry area with a dehumidifier or space heater for 24-72 hours, then re-test.

  • Oven drying: Dry the whole motor in an oven at 80-100°C (below the insulation class limit) for 12-24 hours.

  • Short-circuit current method (small motors): Lock the rotor and feed about 10% rated voltage to heat the windings, watching the temperature rise.

Only continue once the re-test passes.

4. Different Shutdown Durations, Different Effort

  • Up to 1 week: Visual check plus hand-rotation is enough.

  • About 1 month: Add insulation-resistance measurement and grease inspection.

  • Over 3 months: Go through the full 5-step checklist; clean and repack bearings if needed.

  • Explosion-proof motors: Also inspect flameproof joints, fasteners and sealing rings. Restarting a YBX3 flameproof motor in a chemical plant or mine should follow the Ex-standard check by qualified personnel.

5. During and After Start-Up

Even after the checks pass: jog 2-3 seconds to confirm rotation direction; run no-load for at least 30 minutes and watch bearing temperature (should not feel hot to the touch) and vibration; then run at reduced speed under load before full speed. Pay extra attention during the first 24 hours - the failure rate of motors returning to service is slightly higher than steady operation.

If your low-voltage induction motor has been idle for a long time and you are unsure how to handle it, contact the SHANGDIAN (Shanghai Electric Motor Factory) team for inspection and restart guidance.

Contact Phone National Service Hotline :

+86 15523831294

Winning Customer Trust Through Quality
WhatsApp QR Code Scan QR Code
Add Company WhatsApp

Copyright © 2025-2026 Shanghai Electric Motor Factory. All Rights Reserved.  

QR Code WhatsApp

WhatsApp QR Code

Contact Info Contact

+86 15523831294

Call Now Contact
Back to Top Top